Thu, 30 Nov 2023
22.7 C
Durban

Stop/go: Cato Ridge- Dardanelles N3 upgrade enters next phase

Home Infrastructure Construction & Civils Stop/go: Cato Ridge- Dardanelles N3 upgrade enters next phase

CONSTRUCTION work on the upgrade of the N3 from the Cato Ridge Interchange to the northern end of the Dardanelles Cutting, which began in April 2021, is now entering a new phase, which will involve stop/go restrictions.

That’s according to the South African National Roads Agency (SANRAL), which announced that the   patching and re-surfacing of the existing R103, which is the road running alongside the N3, was planned to start on 14 June and should be complete towards the end of July 2021.

There will be stop/go restrictions, but to lessen the impact on peak traffic, the work will be carried out between 9am and 4pm each day.

“Temporary concrete barriers will continue to be erected at night on the right-hand side of both carriageways of the N3 to enable the temporary widening of the southbound to commence. Piling for the foundation of a future bridge at Camperdown Interchange will commence on 21 June 2021,” said Mohamed Parak, SANRAL’s Eastern Region Project Manager.

During all construction activities on the N3, two-lane traffic flow in each direction will be maintained during the daytime, with minimal disruption to the traffic. During night-time, the fast lane will be closed over approximately 2km during the erection of the temporary barriers. This, said Parak, would result in minor delays to traffic.

The current emergency repair works on the N3, which are being carried out at night, are scheduled to be completed by 13 June 2021.

“We appeal to road users to take note of the construction activities and to be observant of the advance warning signs and speed restrictions, when travelling past the construction work zones. Road users are encouraged to plan their trips accordingly, and to make provision for the additional travel time,” said Parak.

Most Popular

Eskom progressing on the implementation of the Transmission Development Plan

ESKOM hosted the Transmission Development Plan (TDP) Implementation Forum on November 15 to give an update on the TDP and to apprise stakeholders of...

Container terminals’ backlog costs business millions, and Transnet nothing

THE South African Association of Freight Forwarders estimates that the 96 vessels waiting at anchorage outside the country’s commercial ports, is costing R98 million...

R1.5bn palm oil plant nears completion at Richards Bay IDZ

PLANS are underway to ensure that more land is acquired to enable local communities to be involved in the production of the raw materials...

Entrepreneurs secure R45m for entry-level recruitment venture

LOCAL online recruitment start-up JobJack has secured R45 million in investment funding in a pre-series A round. The funding round was led by Old...