KZN water projects on track

Home Infrastructure Construction & Civils KZN water projects on track

THE Department of Water and Sanitation in KwaZulu-Natal has reiterated its commitment to implement long-term measures to address water scarcity issues in different parts of the province.

Department spokesperson Sputnik Ratau said the department is on course with the implementation of the Greytown Bulk Water Supply, which is set to provide emergency water relief and long-term water supply to Greytown and Enhlalakahle.

Ratau said Phase 1 of the project included refurbishing and upgrading aging water infrastructure, unclogging drainage systems and the installation of new interconnecting pipes with valve chambers to restore water treatment works to an estimated peak capacity of 6 megalitres per day.

“I can confirm that Phase 1 of the project was successfully implemented and completed in September 2010. We are now rolling out the implementation of Phase 2, which entails the extension of the Greytown Water Treatment Works (WTWs) by 7 megalitres per day.

“The total capacity of the WTW will then be 13 megalitres per day,” Ratau said.

Phase 2 will also include the development of abstraction works at Craigie Burn Dam, raw water pump stations, and bulk conveyance between Craigie Burn Dam and Greytown WTW for capacity of 12 megalitres per day to 16 megalitres per day.

“What this means is that there will be additional potable water storage to maintain specific hours of storage capacity and achieve spatial balance of bulk delivery with the growth of the town.

“This will be through a 2.5-megalitre reservoir at Greytown WTW, an additional 2.5-megalitre reservoir at Enhlalakahle Reservoir and the rehabilitation of the existing 2.5-megalitre Enhlalakahle Reservoir,” Ratau said.

“We are working very closely with UMzinyathi District Municipality as the implementing agent, to ensure accountability and prevent any possible acts of corruption,” Ratau said.

The Greytown Bulk Water Supply Scheme is one of the department’s Regional Bulk Infrastructure Grant Projects.

Ratau said the project is ongoing and further updates will be provided.

“We are committing to be as transparent as possible with the work that is being done on the ground. We are working to ensure water supply, especially in communities still experiencing the negative impact of drought.” – SAnews.gov.za

Most Popular

Bringing a female touch to the technology-obsessed world of cybersecurity

The online world is embroiled in a war. Such a statement may seem exaggerated and dramatic, but the figures paint a different picture. In 2021,...

Transnet security officers granted peace officer status

TRANSNET says the granting of peace officer status to its security officers is an important step in ramping up the fight against cable and...

Auto giant officially reopens Prospecton plant

TOYOTA South Africa Motors (TSAM) has announced that its Prospecton Plant in Durban has resumed operations after production was halted due to damages caused...

Deal sealed on Clairwood logistics park lease

ZacPak has signed a 15-year lease with Fortress Logistics for 15,664m² warehousing space at the Clairwood Logistics Park in KwaZulu-Natal. The facility is expected...