Flexible pricing in renewable energy projects: how to strike a balance

Home Infrastructure Energy – Power Generation Flexible pricing in renewable energy projects: how to strike a balance

By Megan Jarvis & Tyron Theessen, Partners at Webber Wentzel

SOARING costs of commodities and energy have resulted in an unprecedented level of cost uncertainty in the inputs needed for developing renewable energy projects. Cost uncertainty is compounded by the logistical woes being faced by developers in South Africa and elsewhere. Even where component parts are available, they may not be at a cost that is recoverable in terms of the contracts in place with buyers or that is sustainable for suppliers.

According to the International Energy Agency (IEA), in its “Renewable Energy Market Update 2022”, released in May 2022, prices of raw materials and freight costs for renewable energy projects have been rising since the beginning of 2021. By March 2022, it said: “the price of PV-grade polysilicon more than quadrupled, steel increased by 50%, copper rose by 70%, aluminium doubled, and freight costs rose almost five-fold. The reversal of the long-term trend of decreasing costs is reflected in the higher prices of wind turbines and PV modules as manufacturers pass through increased equipment costs.

Compared with 2020, we estimate that the overall investment costs of new utility-scale PV and onshore wind plants are from 15% to 25% higher in 2022.”

Other input costs, predominantly energy, have risen substantially because of the Russia/Ukraine war. For South African developers of renewable plants which rely on imported components, these cost increases will be magnified by the depreciation of the rand against the dollar – especially where the power purchase arrangements are denominated in local currency.

These cost increases have further compounded difficulties, initially arising from pending litigation, in closing projects bid under the Risk Mitigation Independent Power Procurement Programme (which was gazetted on 7 July 2020). Similar issues may be faced if other programmes are delayed and could apply equally where private offtaker deals suffer from their own delays.

In this uncertain environment, where fixed pricing on long-lead items cannot always be secured, developers may be unable to sell power at the prices they bid and still make a profit. The same phenomenon affects other private sector power projects under way, such as those being developed to supply renewable energy to offtakers in the mining and other industries, where the developer has undertaken to supply power at a certain agreed price.

The client in turn has budgeted for that cost and may also have limited room for cost escalations.

Building cost escalations into contracts

Many contracts may have prudently allowed for an annual escalation in tariffs of CPI plus a certain percentage or in line with a formula for certain items. However, although CPI may be a measure of the shifting costs of the CPI basket of goods, the composition of capital costs in renewable energy projects is not reflected by this basket. CPI is also not an immediate measure of international commodity fluctuations, so CPI-linked cost escalations will deliver little comfort if project development timeframes are more limited than the realised effect on the basket.

Even though buyers of power may be sympathetic to these cost pressures, a buyer cannot be expected to give a developer a blank cheque. On the other hand, a developer would be hard pressed to continue with an uneconomic project and it is not in the client’s interest if the developer of the project goes into business rescue and work is suspended indefinitely. Similarly, suppliers and original equipment manufacturers, whose costing is more directly affected by these fluctuating input costs, cannot necessarily absorb this risk and certainly cannot do so indefinitely.

To take some of the guesswork out of making provision for these uncertain costs, pre-emptive clauses can be built into contracts that are currently being negotiated. These include clauses allowing cost price adjustments that are based on industry-specific formulae. Invariably, a level of risk will have to be assumed by the buyer in agreeing to flexible pricing, but this may be mitigated by allowing for repricing of components at specified thresholds, termination for convenience provisions and other commercial arrangements where this risk is shared and managed.

When a contract is already in place, the developer and client would need to consider the terms and may need to discuss and, possibly, renegotiate terms to ensure a viable project.
The key is to conclude a commercial arrangement that is fair to all parties. It needs to balance the interests of all project participants and adequately manage the risk.

Most Popular

Slurry sucker system puts WWT back on track

DEVELOPED by local pump and dredging expert IPR, the SlurrySucker dredging system recently provided the ideal solution for getting the emergency water dams at...

Straddle carriers enhance container handling safety

AS the wellbeing of workers on site becomes increasingly critical in all sectors, industries that operate container handling equipment are taking a closer look...

Supplier partnership ensures construction contractor’s quality

TAKING an unconventional route into the construction sector, EB Construction’s Ben Wagner has built a solid contracting business that serves residential, commercial and industrial...

Crushing and screening customers supported

IN an environment where crushing and screening operations attach great importance to equipment uptime and productivity, an extensive footprint of 11 Sandvik entities in...